DESCRIPTION: Structural stabilization of existing Seawall using large diameter concrete-filled drilled shafts installed just landside of the bulkhead. This will stabilize the rock dike and reduce lateral spreading but will not stop liquefaction of the Embarcadero fill. The new shafts can be used to reinforce the existing bulkheads and serve as a future foundation for new wharves.



SHORELINE STABILIZATION:
TYPE: Geotechnical

SHORELINE LOCATION:
Landside





DESIGN LIFE:

ADAPTABILITY:

IMPACT ON THE WATERFRONT:

CONSTRUCTION COST:
75+ Years

Medium

Minor Landside Intervention

Moderate





SEISMIC HAZARDS MITIGATED:
SEISMIC PERFORMANCE IMPROVED:





Lateral Spreading
Liquefaction

StructuresUtilities & Transportation





MEASURES COMPATIBILITY:
Flood
Seismic
Floodwalls
Raised Marine Structures
Liquefaction Mitigation
Bulkhead Wharf Retrofit

Utility Retrofit




CONSIDERATIONS:

ADVANTAGES:

DISADVANTAGES:





  • The diameter of the shaft would be defined by the depth of Young Bay Mud which varies along the waterfront.
  • Measure less effective in areas of deep Young Bay Mud.



  • Stabilizes shoreline with smallest construction footprint.
  • Can be used to seismically reinforce existing bulkhead wall & wharves.
  • Can serve as a new foundation for future bulkhead wall & wharf replacement.
  • Seismically resilient Promenade can be supported by the shafts.
  • Construction duration likely less than landside buttress shoreline stabilization measure.
  • Waterfront buildings can likely remain occupied during construction.
  • No in-water work.

  • High construction impact to the Embarcadero.
  • Does not mitigate liquefaction-induced settlements of Embarcadero.
  • Requires some utility relocation work.





CONSTRUCTION IMPACTS TO THE PUBLIC:

SEA LEVEL RISE ADAPTATION OPPORTUNITIES:



  • Construction would require lengthy closure of northbound Embarcadero and Promenade.
  • Southbound Embarcadero may be changed to one lane in each direction.
  • Light rail may need to be closed to provide traffic/bike/pedestrian circulation space.



  • Drilled shafts can serve as a future seismically reliable foundation to support a new raised bulkhead wharf or floodwall at the promenade.
  • Groundwater cutoff can be integrated into shaft system by providing smaller diameter secant piles or soil-cement mixing between the shafts to provide a barrier for bayside sea level rise.




DESIGN CONSIDERATIONS:

  • The diameter of the shaft would be defined by the depth of Young Bay Mud which varies along the waterfront
  • Measure is less effective in areas of deep Young Bay Mud.
  • Consider using to reinforce the existing bulkhead wall & wharf (need seismic joint at pier and shed).
  • Consider using as foundation for future bulkhead wall & wharf, design the complete system for incremental construction and built only the shaft portion now.
  • Consider supporting Promenade and creating an earthquake resilient utility corridor.


SITE-SPECIFIC CONSIDERATIONS:

  • Special procedures would be required in the Fisherman’s Wharf area since contaminated soils below the water surface would be excavate by construction operations.
  • Subsurface conditions make a large difference in size and cost, deep Young Bay Mud is very expensive.
  • Where deep YBM, consider other needs for large foundation such as new storm/sewer storage capacity and resilient utility corridors.


URBAN DESIGN CONSIDERATIONS:

  • Construction work to demolish surface infrastructure and to relocate utilities may provide an opportunity to rebuild the Embarcadero and promenade following a new design including reconfiguring the northbound lanes & bike lane.
  • Closure of northbound Embarcadero can provide opportunity for utility and other maintenance or replacement work for seismic improvements and to prevent future disruption.


HISTORICAL RESOURCE CONSIDERATIONS:

  • This measure would not impact any historical buildings nor marine structures.


INSTALLATION AND CONSTRUCTABILITY CONSIDERATIONS:

  • Requires significant utility relocation work. Requires demolition and restoration of promenade.Large construction
  • footprint required for equipment and materials.



Other Types of Seismic Measures:

Click the images and links below to explore other types of seismic measures.

Shoreline Stabilization
Nearshore ButtressLandside ButtressSuper Bulkhead Wharf



Targeted

Bulkhead Wharf RetrofitLiquefaction Mitigation




Head back to the Measures Explorer to check out flood measures.


Measure related to shoreline stabilization opportunities to address seismic risk

Looking for more? Head back to the Measures Explorer to check out other flood and seismic measures.


Installation of large drilled shafts to stabilize the shoreline would require large equipment as shown here - San Francisco, CA ©Fugro
DESCRIPTION: Structural stabilization of existing Seawall using large diameter concrete-filled drilled shafts installed just landside of the bulkhead. This will stabilize the rock dike and reduce lateral spreading but will not stop liquefaction of the Embarcadero fill. The new shafts can be used to reinforce the existing bulkheads and serve as a future foundation for new wharves.



SHORELINE STABILIZATION:
TYPE: Geotechnical

SHORELINE LOCATION:
Landside





DESIGN LIFE:

ADAPTABILITY:

IMPACT ON THE WATERFRONT:

CONSTRUCTION COST:
75+ Years

Medium

Minor Landside Intervention

Moderate





SEISMIC HAZARDS MITIGATED:
SEISMIC PERFORMANCE IMPROVED:





Lateral Spreading
Liquefaction

StructuresUtilities & Transportation





MEASURES COMPATIBILITY:
Flood
Seismic
Floodwalls
Raised Marine Structures
Liquefaction Mitigation
Bulkhead Wharf Retrofit

Utility Retrofit




CONSIDERATIONS:

ADVANTAGES:

DISADVANTAGES:





  • The diameter of the shaft would be defined by the depth of Young Bay Mud which varies along the waterfront.
  • Measure less effective in areas of deep Young Bay Mud.



  • Stabilizes shoreline with smallest construction footprint.
  • Can be used to seismically reinforce existing bulkhead wall & wharves.
  • Can serve as a new foundation for future bulkhead wall & wharf replacement.
  • Seismically resilient Promenade can be supported by the shafts.
  • Construction duration likely less than landside buttress shoreline stabilization measure.
  • Waterfront buildings can likely remain occupied during construction.
  • No in-water work.

  • High construction impact to the Embarcadero.
  • Does not mitigate liquefaction-induced settlements of Embarcadero.
  • Requires some utility relocation work.





CONSTRUCTION IMPACTS TO THE PUBLIC:

SEA LEVEL RISE ADAPTATION OPPORTUNITIES:



  • Construction would require lengthy closure of northbound Embarcadero and Promenade.
  • Southbound Embarcadero may be changed to one lane in each direction.
  • Light rail may need to be closed to provide traffic/bike/pedestrian circulation space.



  • Drilled shafts can serve as a future seismically reliable foundation to support a new raised bulkhead wharf or floodwall at the promenade.
  • Groundwater cutoff can be integrated into shaft system by providing smaller diameter secant piles or soil-cement mixing between the shafts to provide a barrier for bayside sea level rise.




DESIGN CONSIDERATIONS:

  • The diameter of the shaft would be defined by the depth of Young Bay Mud which varies along the waterfront
  • Measure is less effective in areas of deep Young Bay Mud.
  • Consider using to reinforce the existing bulkhead wall & wharf (need seismic joint at pier and shed).
  • Consider using as foundation for future bulkhead wall & wharf, design the complete system for incremental construction and built only the shaft portion now.
  • Consider supporting Promenade and creating an earthquake resilient utility corridor.


SITE-SPECIFIC CONSIDERATIONS:

  • Special procedures would be required in the Fisherman’s Wharf area since contaminated soils below the water surface would be excavate by construction operations.
  • Subsurface conditions make a large difference in size and cost, deep Young Bay Mud is very expensive.
  • Where deep YBM, consider other needs for large foundation such as new storm/sewer storage capacity and resilient utility corridors.


URBAN DESIGN CONSIDERATIONS:

  • Construction work to demolish surface infrastructure and to relocate utilities may provide an opportunity to rebuild the Embarcadero and promenade following a new design including reconfiguring the northbound lanes & bike lane.
  • Closure of northbound Embarcadero can provide opportunity for utility and other maintenance or replacement work for seismic improvements and to prevent future disruption.


HISTORICAL RESOURCE CONSIDERATIONS:

  • This measure would not impact any historical buildings nor marine structures.


INSTALLATION AND CONSTRUCTABILITY CONSIDERATIONS:

  • Requires significant utility relocation work. Requires demolition and restoration of promenade.Large construction
  • footprint required for equipment and materials.



Other Types of Seismic Measures:

Click the images and links below to explore other types of seismic measures.

Shoreline Stabilization
Nearshore ButtressLandside ButtressSuper Bulkhead Wharf



Targeted

Bulkhead Wharf RetrofitLiquefaction Mitigation




Head back to the Measures Explorer to check out flood measures.


  • Thank you for learning about ways to strengthen the waterfront through the Measures Explorer! Please share your feedback on the Drilled Shaft measure.

    Would you like to see it prioritized as a potential solution along San Francisco's waterfront? Do you have any concerns or input you would like to share about this measure?

    The Port wants to hear from you!

    Share Feedback